MicroLink Customer C-01  /  Rev A
Customer proposal  ·  C-01

Customer Proposal

Capacity on a site that already has power. Reserved critical IT load, priced per kilowatt month on the instrument you already sign. What changes is where the load sits and what leaves the building with the heat. Two units of sale: a 1.25 MW pod inside an energised industrial partner site, and a 10 to 45 MW liquid cooled facility.

USD 154Per kW per month, power excluded and passed through at cost
48+ monthsAverage primary market grid connection wait. We are not in that queue
Below 0.5Energy reuse, reported alongside a 1.12 PUE design point and never instead of it
What you sign, in order, one mark per document
Mutual NDA, before anything else Capacity and data request, then site return Heads of terms, master agreement, service order, onboarding
Track A
1.25 MW IT load pod, repeatable
Track B
10 to 45 MW liquid cooled facility
Rate
USD 154 per kW month, power excluded
Term
15 years, 3.0 percent fixed escalator
Density
50 kW to above 100 kW per rack position
Revision
A

The Offer

You buy reserved critical IT load in megawatts, priced per kilowatt per month, modified gross plus electric, with metered power passed through at cost. That is the instrument your existing colocation and wholesale agreements already run on. Nothing about how you contract has to change. What changes is where the load sits, how quickly it can be energised, and what leaves the building with the heat.

Two units of sale sit inside the same architecture. Track A is a 1.25 MW IT load pod delivered to an operating industrial or municipal partner facility and tied in behind an existing meter. It repeats on one partner interface until the site is full, so the increment is small and the ceiling is whatever the partner can carry.

Track B is a 10 to 45 MW liquid cooled facility, contracted in halls or suites, with the full security, certification and carrier furniture a regulated buyer expects around the capacity it takes.

Both are direct liquid cooled to the cold plate at a capture fraction of 0.85, on a facility loop at 32 °C flow (90 °F) and 42 °C return (108 °F). Both reject the full duty through a dry cooler field that carries the load on its own, so recovered heat is upside and never a condition of your availability.

Power for the compute load is bought at the site price and passed through at cost. We take no margin on the energy line. It moves with the site rather than with us.

The two tracks, side by side, on the same architecture
ElementTrack A, the podTrack B, the facilityCommon to both
Unit of sale1.25 MW IT load per pod, thirteen rack positions10 to 45 MW IT load, taken in tranches of roughly 1 to 5 MWReserved critical IT load in MW, priced per kW month
CoolingDirect liquid to the cold plate, 0.85 captureSame architecture at hall scale32 °C flow (90 °F), 42 °C return (108 °F), 10 K rise
Heat rejectionDry cooler field carries the whole duty aloneDry cooler field carries the whole duty aloneRecovered heat is upside, never a dependency
SitingBehind an existing meter at a partner already carrying firm loadA shell on or adjacent to a partner parcelEnergised site, not a queue position
Facility furniturePartner site security, module certification, one defined network handoffFour layer security, carrier neutral meet me room, full certification stackComponent level service level in both cases
Energy marginZeroZeroPass through at the site price
Metric first with imperial in brackets throughout this document. Track B figures are design position; the pod figures follow the design record.

Reserved critical IT load in megawatts, priced per kilowatt month. The instrument does not change. The site underneath it does.

Speed to Power

Speed to power is now the first criterion in site selection, ahead of community support, latency and proximity to customers. Power availability rather than capital is the principal constraint, and a will serve letter is not powered land. MicroLink starts at a tie in to a partner that is already carrying firm load, so no interconnection application opens at any step.

48+Months average primary market grid connection wait, five to six years in constrained submarkets
1.6 pctNorth American colocation vacancy, a record low
73 pctOf the North American pipeline pre leased before completion
Under 200 mBuried soft dig from the tie in point (656 ft)
Critical path, new build against behind the meter
NEW BUILD, GRID INTERCONNECTION LOAD STUDY, QUEUE UPGRADE SCOPE BUILD COMMISSION 48 months and above in primary markets MICROLINK, BEHIND THE METER SURVEY QUALIFY TIE IN LIVE The interconnection application never opens Existing energised load, single point tie in at 480 VAC three phase, under 200 m (656 ft) of buried soft dig

What is not on the critical path

  • No interconnection queue position
  • No load study on a utility timetable
  • No upgrade scope to negotiate
  • No transformer on a 128 week lead time
  • No new large load connection request

What is

  • The site survey and the data request
  • Partner capacity confirmed deliverable
  • Module build and delivery
  • Tie in and commissioning
  • Your own hardware lead times

What we need from you

  • Capacity required in MW
  • The date it has to be live
  • Rack density and platform
  • The market or region it has to sit in
  • Any residency or certification constraint

A queue position is not capacity and a will serve letter is not powered land. The only schedule that binds here is the survey, the module build and your own hardware.

Technical Requirements

Direct liquid cooling to the cold plate at a capture fraction of 0.85. Facility loop at 32 °C flow (90 °F) and 42 °C return (108 °F) on a 10 K rise, inside the supply window the current rack scale platform specifies. Busway distribution at row level rather than a power distribution unit per rack. Structural design to the concentrated rack case.

1.29 MWthRejection duty at 1.25 MW IT load, carried in full by the dry cooler field alone
0.85Liquid capture fraction to the cold plate
10 KLoop rise, 32 °C flow and 42 °C return
480 VThree phase, single point of connection
S-303  Thermal chain from cold plate to rejection and to the partner
YOUR AVAILABILITY SITS ON THIS PATH COLD PLATE0.85 capture COOLANT DISTRIBUTION32 / 42 °C loop DRY COOLER FIELDFull duty, always available No evaporative draw. No water treatment. No discharge permit change. The dry cooler field is sized to reject 100 percent of the duty with no thermal offtake at all. UPSIDE, AND NEVER A CONDITION OF YOUR SERVICE LEVEL HANDOVER EXCHANGERPartner boundary PARTNER PROCESS55 °C native, 70 °C boosted Delivered heat is metered on EN 1434 and settled with the partner, not with you. Partner thermal demand is outside your service level by design. If they take nothing, your capacity is unaffected.

Heat leaves by one of two routes and both are built. The dry cooler field carries the whole duty on its own, so partner thermal demand is upside rather than a dependency in your availability calculation.

Service Level

A Tier label certifies a design. The contract is what binds operations. The service level here is written per component class, with penalties attaching to the liquid cooling circuits by name rather than only to the electrical path, because a synchronised training run does not fail gracefully. It goes back to the last checkpoint.

What is covered, how it is written, and why
ElementPostureWhy it is written this way
Electrical path99.982 percentPower is responsible for 45 percent of serious outages in the published outage analysis. Tier III equivalence is 99.982 percent, or 1.6 hours a year.
Liquid cooling circuitsN+1 explicitPenalties attach to the cooling circuits by name. A liquid cooled hall fails differently from an air cooled one and the contract has to say so.
Block exclusivityDedicatedIT power guaranteed in kilowatts, not in rack equivalents. No resource contention with another tenant during a demand squeeze.
Mean time to repairIn writingStated per component class rather than as a single facility number.
Partner heat demandNot a dependencyDeliberately outside your service level. The dry cooler field carries full duty whether the partner takes heat or not.
Density overrunWrittenClause already standard in the market
Component level availability, N+1 on the direct liquid cooling circuits, penalties on cooling, and MTTR in writing are the four elements current AI colocation practice treats as the minimum defensible set.

Commercial Terms

USD 154 per kilowatt per month, power excluded, on a 15 year base term with a 3.0 percent fixed escalator. That is the MicroLink reference of USD 1.85M per MW of IT per year expressed per kilowatt month. Market figures below are asking rates rather than transacted rates, and vary by market and by deployment size.

USD per kW per month, against the published market bands
Per kW per month, scale 0 to 400
MicroLink
154
154
Hyperscale
100 to 150
100 to 150
Wholesale colo
150 to 250
150 to 250
Retail colo
200 to 400
200 to 400
US wholesale average 195.94, CBRE H2 2025
Commercial terms against the 2026 market standard
TermMicroLinkBracketMarket position
RateUSD 154 per kW monthWholesaleWholesale colocation asks 150 to 250. Hyperscale asks 100 to 150. The US wholesale average was 195.94 in H2 2025.
PowerPass through at costModified gross plus electricOperators typically bill a markup over their own wholesale energy cost. Electricity related charges are 30 to 50 percent of colocation revenue.
Tenor15 yearsAnchorWholesale and hyperscale anchor leases run 10 to 15 years.
Escalator3.0 percent fixedFixedMarket is index linked or fixed at 3 to 4 percent on long terms.
Increment1.25 MW per pod, or 1 to 5 MW tranches in a facility250 kW to 4 MWAI campus leases contract at 100 to 300 MW and the unit repeats to reach them.
StructurePower floor, take or payStandardBase rent anchored to reserved MW from the end of a defined ramp, with termination economics tied to the net present value of remaining rent.
Our margin on energyZeroAt the site pricePower reaches you at what the site pays. It moves with the site rather than with us.
Rate excludes power in every line above. PUE cap: market leases cap tenant exposure at 1.3 to 1.4 and put the excess on the landlord. The design point is 1.12, so the cap is not the binding term in this deal.

Seventy to eighty percent of operator revenue is base rent on reserved capacity. Fifteen to twenty percent is metered power, where operators typically take a markup. We take none.

Efficiency and Reuse Reporting

Everyone quotes PUE, and a conventional hall can reach a competitive one. It cannot report an energy reuse figure at all, because it has nowhere to send the heat. Where you operate in Europe that is already a compliance line. Where you operate in the United States it is the disclosure your competitors will be asked about next.

1.12PUE design point, against market lease caps written at 1.3 to 1.4
Below 0.5Energy reuse effectiveness, reported alongside PUE and never instead of it
EN 1434Metering basis. Delivered heat measured and settled
50600-4-6DIN EN reuse fraction definition, so the claim is auditable
Reuse is already regulated where you operate
JurisdictionRequirementThresholdFrom
Germany, EnEfG section 11Energy reuse factor, new data centers10 percentJuly 2026
Germany, EnEfG section 11Energy reuse factor15 percentJuly 2027
Germany, EnEfG section 11Energy reuse factor20 percentJuly 2028
Germany, EnEfG section 11PUE ceiling1.2July 2026
Germany, EnEfG section 11Renewable supply100 percentJanuary 2027
European UnionEnergy Efficiency Directive recast, waste heat recovery at 1 MW and above, or a demonstration that it is not technically feasibleIn forceMember state transposition
The metric named in the standards and in the German regulation is the energy reuse factor. ERE is reported alongside PUE in MicroLink material; where a regulator asks for ERF, the same metered basis produces it.

A reuse figure is only worth reporting if it survives diligence. Delivered heat is metered on EN 1434 and the reuse fraction is defined by DIN EN 50600-4-6, so the number holds in a diligence pack rather than only in a press release.

Facility Standards

If your capacity carries a regulator, an auditor or a card scheme behind it, the questions arrive before the rate does. This section states what the 10 to 45 MW facility carries in full, and what a pod inside a partner site carries instead, without pretending the two are the same.

Physical security, treated as four layers
LayerWhat sits in itTrack A, the pod
Perimeter and siteMulti layer fencing and anti climb barriers, thermal perimeter cameras and ground radar, crash rated gates and bollards, 24/7 guardhouse patrols, integrated security lightingThe partner's own site regime
BuildingConcentric zoning from public through reception, controlled, secure operations and critical infrastructure to white space, with active authentication at every transition boundaryNot available inside a partner building
Identity and accessBiometric and facial recognition, multi factor by card, PIN and biometric, role based and time bound permissions, an audit trail for every door cycle, escort policyModule level access control and logging
Data hall and rackDual authentication mantraps at hall entry, customer cages and isolated private suites, electronic cabinet locks, cabinet access logging, continuous tamper detectionCabinet locking, access logging and tamper detection
Surveillance sits across all four: behaviour analytics, object and vehicle recognition at the gates, thermal and 4K imaging, automated alerting into a security operations centre, and a stated video retention period.

Certification stack

  • ISO 27001, information security
  • ISO 22301, business continuity
  • ISO 9001, quality management
  • SOC 2 Type II
  • PCI DSS readiness
  • NIST cybersecurity framework
  • SWIFT customer security programme
  • Data residency stated per site

Fire and environment

  • Very early smoke detection, plus ceiling and under floor detectors
  • Physical fire zoning and compartmentation
  • Double interlock pre action, zero residue clean agent
  • Emergency smoke extraction, continuous monitoring
  • NFPA 75
  • Temperature, humidity, power quality, smoke
  • Flood and leak detection on the liquid path

Network and isolation

  • Carrier neutral core, multiple dedicated carriers
  • Dark fibre routing and duct ownership options
  • Private tunnels, your own equipment and topology
  • Management and production separation
  • Out of band management
  • Firewalls with intrusion detection and prevention
  • Micro segmentation and denial of service protection
Two lenses, and which one this proposal is written to
LensWhat you are buyingWhat the agreement carries
HyperscaleInfrastructure as a controlled asset. Contiguous space, raw density, dark fibre and duct ownership, no bottlenecksPower floor, ramp with hard dates, expansion options, density overrun, cross connect
EnterpriseInfrastructure as a managed risk. A single point of accountability, turnkey capacity and an uptime guaranteeAll of the above plus the security schedule, the certification schedule, residency and continuity
Track A serves the hyperscale lens cleanly. Whether it serves an enterprise lens buyer without a guardhouse, a meet me room and a mantrap sequence is stated here as an open question rather than claimed either way.

A pod is one envelope inside somebody else's building. It cannot offer a reception zone or a meet me room, and this document does not claim it can. What it offers instead is module level certification, cabinet level control and a single defined network handoff.

Scale

The pod is not a competitor to a campus lease. It is the unit that lands inside an energised site while a campus is still in a queue, and it repeats on the same partner interface and the same thermal architecture until the site is full. Nothing about the design changes between one pod and the campus that follows it. What changes is how many sit on the slab.

Scale ladder, one thermal architecture throughout
ONE THERMAL ARCHITECTURE THROUGHOUT EDGE30 kW POD1.25 MW IT, 13 racks MULTI POD SITEOne partner interface FACILITY10 to 45 MW, halls and suites AI campus leases contract at 100 to 300 MW. The unit repeats toward them rather than competing with them. Expansion options are pre priced on additional capacity at the same site, exercisable inside a defined window. Exercise is conditioned on partner capacity being confirmed deliverable, and that condition is written rather than assumed.
The community position, and what each claim rests on
ClaimEvidenceWhat it rests on
No new demand on the gridBehind the meterCapacity sits behind an existing meter rather than arriving as a new large load connection request.
Gas displaced on siteMeteredDelivered heat replaces combustion at the partner, measured and settled on EN 1434.
An industrial site stays openPer partnerThe thermal payment lands on the partner's operating cost rather than on a landowner's rent.
Reported on a standardDIN EN 50600-4-6The reuse fraction is defined and auditable, so the claim holds in a diligence pack.
These are the four claims that survive diligence, and they are the sentences a policy team can use in a planning hearing.

Basis and Sequence

Bring the megawatts and the date. We come back with the sites that hold it, the rate at your term, and the reuse figure you get to report. Nothing beyond the mutual non disclosure agreement is signed before that return exists.

The document chain

C-04
Mutual NDA. The first and only document signed before the capacity return.
C-02
Capacity and data request. A fixed list, so every requirement is assessed on the same basis.
C-05
Heads of terms. Sets the shape of everything below it before any of it is drafted.
C-10
Master services agreement. Signed once, solution agnostic, carrying definitions, liability, insurance, data and term.
C-11
Service order. Per deployment. Reserved MW, rate, term, escalator, ramp tranches with dates, site, density and platform.
C-12
Onboarding document. Access, remote hands, change control, escalation, acceptance testing, delivery logistics.

Schedules hang off the master agreement and are selected per track: service levels, security and compliance, thermal and reuse reporting, metering and billing.

Sequence to live

01
You send capacity in MW, the live date, rack density and platform, the market it has to sit in, and any residency or certification constraint.
02
We return candidate partner sites with metered thermal demand, the tie in position, the rate at your term, and the reuse figure each site supports.
03
Site qualification against the fixed data request, and the partner interface specification is issued.
04
Capacity contracted at design freeze, on the master agreement and a service order.
05
Build, tie in, commission, acceptance test, live.

What is stated and what is not

Track A figures follow the design record. Track B figures are design position rather than delivered precedent, and are marked as such wherever they appear. MicroLink holds no letter of intent at any site and is not in pre construction; site status is confirmed partner interest.

  1. Rate is the MicroLink reference of USD 1.85M per MW of IT per year expressed per kilowatt month, power excluded in every line.
  2. Market rate brackets and the US wholesale average of 195.94 are CBRE H2 2025 asking rates rather than transacted rates, and vary by market and by deployment size.
  3. Speed to power, vacancy at 1.6 percent and the 73 percent pre lease figure are per the published 2026 outlooks. Tier III equivalence at 99.982 percent and the 45 percent power share of serious outages are per the published outage analysis.
  4. Reuse thresholds are as adopted in the German Energy Efficiency Act and the recast EU Energy Efficiency Directive. The metric named in the standards and the regulation is the energy reuse factor.
  5. Facility security, certification, fire, environmental and network content in section 07 states the market expectation set for a facility of this size. It applies in full to track B. Track A positions are stated separately in the same tables.

Next Steps

You sign the instrument you already sign, at a rate inside the wholesale band, with the energy line taken out of our margin. What you get that a conventional hall cannot give you is a live date that does not depend on a queue, and a reuse figure you get to report. Bring the megawatts and the date.